Tata Power Company Limited
Tata Power approves ₹11,871 crore for 1,800 MW Shirwata pumped storage project with 51-month timeline
Capacity addition
Main disclosure
- The Board of Directors of Tata Power Company Limited has approved an investment in the 1,800 MW Shirwata Pumped Storage Project in Maharashtra.
- Existing capacity stands at 16.9 GW, with the proposed addition of 1,800 MW.
- The proposed capacity addition is to be completed over 51 months.
- Investment required: ₹11,871 crore.
- Financing plan: debt 75% and equity 25%.
- Rationale: Pumped Storage Hydro Project will enable Renewable Energy Round the Clock applications, energy shifting and decarbonisation of hard-to-abate industries.
Disclosure and timing
- The disclosure was made under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, and the information is also available on the company's website.
Filing and date context
- Filing date: November 11, 2026.
- The information is communicated to NSE (Scrip Code: 500400).