Monitoring Agency reports no deviation from IPO objects but notes deployment delays and unutilised proceeds for Vikram Solar as of 30 September 2026
Key Monitoring Agency findings and approvals status
Deviation from the objects: No deviation observed.
Means of finance for the objects: Not changed.
Government/statutory approvals related to the objects: Partly obtained; management representations indicate requisite approvals secured for the current stage.
Delay in deployment and implementation: The MA notes delays; revised timelines show Phase I Module 3 GW moved to June 2026, Phase I Cell 3 GW to December 2026, and Phase II Module 3 GW to June 2026.
Overall activity status: The MA notes ongoing deployment, with some common infrastructure costs allocated between Phase I and Phase II.
Utilization of IPO proceeds and deployment status (as of 30 Sept 2026)
Utilised INR 35.19 million for purchase of a Guest House, which the company states will be used by the Project Team and treated as project cost.
Total deployment of IPO proceeds up to the quarter end: INR 13,230.89 million; during the quarter: INR 5,109.31 million; leaving unutilised proceeds of INR 1,769.11 million.
Objects and funding mix disclosed: Phase I expenditure of INR 7,697.30 million; Phase II expenditure of INR 5,952.08 million; General Corporate Purposes INR 495.49 million; total outlay (A) INR 14,144.87 million; offer-related expenses (B) INR 855.13 million; combined total INR 15,000 million.
The timeline for trial runs and first production cited in the prospectus has been revised; Phase I Module 3 GW now targeted by June 2026, Phase I Cell 3 GW by December 2026, and Phase II Module 3 GW by June 2026.
Object progress and revised timelines
Phase I Project – Module 3 GW: original schedule March 2026; revised to June 2026; delay ~3 months.
Phase I Project – Cell 3 GW: original schedule September 2026; revised to December 2026; delay ~3 months.
Phase II Project – Module 3 GW: original schedule March 2026; revised to June 2026; delay ~3 months.
Notes show a separate delay entry of about 6 months across items in the delay table, with ongoing implementation.
Deployment of unutilized IPO proceeds and investments
Unutilised IPO proceeds as of 30 September 2026 total INR 1,769.11 million.
Unutilized proceeds are invested in fixed deposits across Canara Bank and State Bank of India for Vikram Solar Limited and its subsidiary VSL Green Power Private Limited; total FD investments amount to INR 1,853.19 million (grand total INR 1,853.55 million including a small balancing amount).
Details include multiple Canara Bank and SBI deposits with various maturities (e.g., deposits maturing in 2026–2027).
Related-party transactions and cost allocations
Notes on related-party transactions include INR 0.10 million paid to Viki.Ai Private Limited and INR 38.49 million to VSL RE Power Private Limited.
Wholly owned VSL Green Power Private Limited paid INR 11.34 crore to Vikram Solar Limited for consultancy services.
Vikram Solar FY27 Q2: EBITDA per watt up 37% QoQ; 1.7 GW orders; 9 GW cell facility on track
Key financials and mix
Revenue from operations grew 17.7% in H1 FY27 versus H1 FY26.
EBITDA per watt improved 37% sequentially, reflecting a better quality mix and execution.
7 GW of new orders added in Q2 FY27, higher than 0.8 GW in Q1 FY27.
DCR share rose to 22% in Q2 FY27 from 7.5% in Q1 FY27.
Distribution and retail volumes increased to 44% in Q2 FY27 from 14% in Q1 FY27.
Net debt/equity stood at 0.17x as of 30 September 2026.
Capacity expansion and roadmap
9 GW N-type TOPCon cell facility at Gangaikondan on schedule; first cells expected in December 2026, with phased full commissioning.
9 GW ingot and wafer capacity at the same site targeted by FY29 as part of end-to-end integration.
VSL PowerHive: 7.5 GWh/year BESS plant at Oragadam, inaugurated January 2027; commercial operations from April 2027; cell manufacturing capacity planned at 7.5 GWh from 2028.
Strategic emphasis on domestic supply-chain indigenization and improved asset utilization to support higher DCR volumes.
Ratings, recognitions and sustainability
India Ratings: long-term rating IND A+/Stable and short-term rating IND A1+.
EcoVadis Platinum Medal 2026 with a score of 88/100.
Kiwa PVEL Top Performer (9th time) and BloombergNEF Tier 1 manufacturer emergence in recent quarters.
Management outlook and focus
Management indicates focus for H2 FY27 is to convert executable orders, improve asset utilization, increase DCR volumes and commission the cell project in a disciplined manner. The overall tone remains positive about long-term opportunities, with progress measured through execution and cash generation.
Vikram Solar approves unaudited standalone and consolidated Q2 FY27 results; notes safeguard duty receivable and disputed liquidated damages; IPO proceeds utilisation update
Board approval of unaudited financial results
Board of Vikram Solar Limited approved the unaudited standalone and consolidated financial results for the quarter and six months ended 30 September 2026 (Q2 FY27), along with the Limited Review Report by GARV & Associates.
Material notes and contingencies
Note 6: safeguard duty amounting to Rs. 1,485.20 million is considered receivable and no provision is required due to ongoing legal proceedings; adjustments will be made based on the outcome.
Note 7: Rs. 527.90 million (included in Trade Receivables) has been withheld/recovered by certain customers related to EPC and other contracts for Liquidated damages, generation loss, etc.; matter referred to dispute resolution/arbitration/court; management expects resolution favorable to the company with adjustments as outcomes occur.
IPO history and proceeds utilisation
During the year ended March 31, 2026, the company completed an IPO of 62,631,604 equity shares; listing on NSE and BSE occurred on August 26, 2025.
Total IPO offer expenses: ₹21,196.74 million (inclusive of taxes); utilisation of IPO proceeds up to September 30, 2026: ₹12,375.76 million; unutilised ₹1,769.11 million.
Utilisation categories included partial funding of capital expenditure via funding to VSL Green Power Private Limited (Phase I and Phase II) and general corporate purposes.
Subsidiaries and group structure
Annexure-1 lists the group components: Vikram Solar GmbH (Germany), Vikram Solar Pte. Ltd. (Singapore), VSL Green Power Private Limited (India), Vikram Solar Foundation (India), VSL Powerhive Private Limited (India), VSL Recycle Services Pvt Ltd (India), Vikram Solar US Inc (USA), Vikram Solar Australia Pty Ltd (Australia), Solarcode Vikram Management GmbH (Germany) and Solarcode Vikram Solarkraftwerk 1 GmbH & Co KG (Germany).
Vikram Solar schedules Q2 & H1 FY27 earnings call for November 16, 2026 at 11:00 IST
Event details
Q2 & H1 FY27 earnings conference call scheduled for Monday, November 16, 2026 at 11:00 AM IST.
Hosted by EY LLP; company participants include Mr. Sameer Nagpal – Chief Executive Officer; Mr. Ranjan Jindal – Chief Financial Officer; Mr. Arun Mittal – Chief Executive Office, VSL PowerHive Private Limited; Miss. Rinal Shah – General Manager – Corporate Finance.
Call-in details provided; pre-register via Diamond Pass; registration link to access the call.
Dial-in numbers: India +91 22 6280 1107, +91 22 7115 8008; United Kingdom 08081011573; Singapore 8001012045; Hong Kong 800964448; United States 18667462133.
Note: The schedule is subject to change due to exigencies.
Contacts
For further information contact: Vikash Verma; Shashank Ganesh.