Sandur to invest ₹280 crore in beneficiation plant; targets 1.7 MTPA upgraded ore by 2027
Key capex plan and first-half financial highlights
The company plans to invest ₹280 crore in its first in‑mine beneficiation plant at Deogiri to upgrade ore from about 50% Fe to more than 60% Fe.
The first 3.5 MTPA unit is expected to produce 1.0–1.2 MTPA of upgraded ore initially, with potential output up to 1.7 MTPA.
Commissioning is targeted for August 2027.
Funding will be through a mix of debt and internal accruals.
The beneficiated material could support ironmaking within the group’s integrated steel value chain.
Mine-head location is expected to reduce waste-ore transportation and aid tailings management; the project is estimated to generate 150–200 direct and indirect jobs.
Consolidated Q2 FY27 results show total income ₹1,519 crore, EBITDA ₹391 crore and PAT ₹261 crore, up 22%, 37% and 88% YoY respectively.
For H1 FY27, consolidated total income ₹2,909 crore, EBITDA ₹749 crore and PAT ₹489 crore, up 21%, 25% and 60% YoY respectively.
MoEFCC grants EC enabling Sandur mine to raise iron ore to 9.42 MTPA and manganese to 0.7330 MTPA
Environmental clearance scope and key capacity changes
MoEFCC granted Environmental Clearance (EC) to the iron ore and manganese ore mine (Mining Lease No. 2678) under EC Identification Number EC26A0000KA5280635N, dated 11 November 2026.
RoM capacity for iron ore increased from 7.85 MTPA to 9.42 MTPA.
RoM capacity for manganese ore adjusted from 1.34 MTPA to 0.7330 MTPA.
Beneficiation plant reconfiguration from 1 x 7.00 MTPA to 2 x 3.5 MTPA.
Downhill Conveyor System remains unchanged at 1.2 km within the mining lease area of 1860.10 hectares.
Waste handling remains per the Indian Bureau of Mines approved mining plan.
Regulatory actions and next steps
Company will initiate further regulatory approvals required to operate at the enhanced production levels.
Stock Exchanges have been requested to record the EC notification.
Sandur Manganese: Independent Director Kundargi completes term; appointed Non-Executive Director from 12 November 2026.
Main disclosure
G. P. Kundargi's second term as Independent Director ends on 11 November 2026 and he will cease to be an Independent Director.
The Board has appointed him as a Non-Executive Director with effect from 12 November 2026, liable to retire by rotation, subject to shareholders' approval.
This appointment follows the board's intimation in letter No. SMIORE / SEC / 2026-27 / 59 dated 3 November 2026.
The change is disclosed pursuant to Regulation 30 read with Schedule III of SEBI (LODR) Regulations, 2015 and related amendments.
Background and term history
At the 67th AGM held on 22 September 2021, G. P. Kundargi was re-appointed as an Independent Director for a second five-year term from 12 November 2021 to 11 November 2026 (not liable to retire by rotation).
The current movement reflects completion of that term and transition to a Non-Executive Director role.
Annexure A: SEBI LODR details
Annexure A provides the reason for change, appointment/cessation dates, and relationships: Brief profile Not Applicable; Disclosure of relationships Not Applicable.
Regulatory filing and record updates
Stock exchanges were requested to take the change on record; the filing includes Annexure A and accompanying communications dated 11 November 2026.