Showing the latest 10 filings. Sign in to filter or browse the full history.
10 of 68 filings·Updated 20 Nov 2026
Showing 10 of 68 filings.
20 Nov 20261 filing
Company UpdateEarnings Call Transcript
Glen Industries reports robust H1 FY27 with expansion plan underway; new facility to start Jan 2027 and full ramp expected by FY28/29
Half-year financial performance and product mix
Revenue from operations for the first half of FY27: INR 115.30 crores, up 20.66% YoY from INR 95.56 crores; total income: INR 116.47 crores, up 20.62% YoY from INR 96.56 crores.
EBITDA: INR 22.71 crores; EBITDA margin 19.5%. Finance cost: INR 4.29 crores, down 11.16% from INR 4.82 crores.
Profit before tax: INR 14.30 crores; net profit: INR 10.91 crores; net profit margin: 9.37%.
Planned new manufacturing facility near Kolkata in Howrah with expanded capacities: 13,109 MT/year additional plastic food-container capacity, taking total to 21,095 MT/year; 7,696 MT/year paper products capacity (including paper cups).
Project staged for completion in phases starting January 2027: Phase 1 capex INR 100.49 crores for new facilities and automation; Phase 2 product-diversification; Phase 3 sustainability initiatives including recyclable/biodegradable materials and EV injection machines.
Preliminary revenue expectation from the new facility: INR 300–350 crores; first-year realization projected at INR 25–40 crores depending on ramp.
Capex total remains INR 130 crores; existing depreciation around INR 7 crores per year; incremental depreciation of INR 10–11 crores post-implementation (total depreciation ~INR 17–18 crores).
Timeline, leverage and financial outlook
Injection molding to start by January 2027; thermoforming and paper products to follow; full production across three divisions expected by April 2027.
Debt position: by year-end total term loans around INR 55 crores (about INR 5 crores existing plus INR 50 crores new); cost of debt ~8–8.5%. Working capital liability about INR 80 crores; total liability around INR 290 crores.
Export focus: current export share ~26% of revenue; target export share to ~35% over the medium term; plans to scale via trade shows (PEC Expo USA, Canton Fair, NRA Show) and broader penetration.
Outlook, margins and strategic positioning
FY27 revenue guidance around INR 225–230 crores; by FY28–FY29 full impact of capacity expansion expected, with turnover around INR 550 crores and EBITDA margin around 18–19%. Projected FY29 PAT approximately INR 52 crores (assuming ~INR 550 crores turnover, ~18% EBITDA, ~INR 15 crores interest and ~INR 18 crores depreciation).
Pricing and raw material: raw-material prices have risen; management indicated price increases of about 35% since Gulf/Middle East period and indicated pass-through capability; margin stabilization targeted at 18–19% with full-capacity operations.
Phase 2 expansion to push volume in thermoforming and IML offerings; expected to support premium pricing and broaden customer base (sweet manufacturers, institutional buyers) with potential for higher wallet share.
New capacity ramp expected to stabilize by Sep–Oct FY28; by then full-year turnover could be INR 400–500 crores in the base scenario, with accelerated growth as the new lines mature.
Capital structure, governance and strategic actions
Post-expansion debt remains manageable; cost of debt ~8–8.5% with improving working-capital efficiency.
Awaiting potential listing on the main board after 3 years; some group entities (e.g., Glen Realty, Glen Paper) are in dormant or trading activity phases; group-wide capital-allocation to be concentrated on Glen Industries' expansion.
Delays in the project were attributed to elections and West Bengal monsoon; management indicated civil work is progressing and injection facilities are targeted to start in January 2027.
Transcript of the Investors Meet will be uploaded in due course on the Stock Exchange and on the company's website www.glen-india.com as per prescribed timelines under the Listing Regulations
Glen Industries project update: regulatory approvals in place; PEB contracted; IPO proceeds fully utilized; production targeted Q4 FY26-27
Regulatory approvals and site readiness
Land conversion from agricultural to industrial has been successfully completed.
Site preparation: land filling work has been completed.
No Objection Certificate / Consent to Establish (CTE) obtained from the West Bengal Pollution Control Board.
Fire NOC / Fire Safety Report (FSR) received from the West Bengal Fire & Emergency Services.
WBSEDCL electricity final sanction letter for sanction of power received; electricity agreement is being executed.
Building Plan sanction received from Zila Parishad.
With these approvals, all regulatory approvals are in place to execute project implementation.
Construction and design
Contract for the Pre-Engineered Building (PEB) structure has been awarded and erection work has commenced.
Piling work has been completed; foundation work is expected to be completed by end-October 2026; delay attributed to excessive rain.
Procurement
Orders for all plant and machineries have been placed.
Order for utility equipment has been placed.
Timeline, delays and reasons
Commercial production was originally expected by Q4 FY2025-26, later extended to Q3 FY2026-27; now expected by Q4 FY2026-27.
Delay factors include:
SIR and election in West Bengal caused delays in building plan approval; final sanction received in July 2026 due to nonfunctioning of Zila Parishad.
Excessive rain delayed piling and foundation work after plan approval.
Delay in sanctioning power to the project due to SIR and election process.
All delays are outside the company’s control.
IPO proceeds utilization
The company has fully utilized the IPO proceeds in accordance with the objects and purposes specified in the Prospectus; no unutilized IPO proceeds remain as on date.
Glen Industries invites analysts to H1 FY27 earnings call on Nov 18, 2026
Event details
Analysts’/investors call on the unaudited consolidated and standalone financial results for the half year ended September 30, 2026 will be held on Wednesday, 18 November 2026, starting at 12:00 PM.
Purpose: discuss the company's H1 FY27 unaudited results.
Joining details: Diamond Pass login and universal dial-in options; dial-in numbers are +91 22 6280 1446 and +91 22 7115 8389; please dial in 10 minutes before the scheduled start.
Notes: Statements during the call may be forward-looking and are subject to risks and uncertainties; actual results may differ; the company and management are not responsible for actions taken based on such statements.
Company UpdateReg. 32 (1), (3) - Statement of Deviation & Variation
Monitoring Agency finds no deviation in Glen Industries IPO proceeds utilization for quarter ended September 30, 2026
Main disclosure: no deviation in IPO proceeds utilization for the quarter
Infomerics Monitoring Agency reports Nil deviation from the objects and Nil range of deviation for the quarter ended September 30, 2026.
Net proceeds from the IPO: Rs. 56.59 crore (Total IPO proceeds Rs. 62.94 crore minus IPO-related expenses Rs. 6.35 crore).
Utilisation status as of September 30, 2026: Rs. 44.00 crore spent by June 30, 2026 and Rs. 12.59 crore spent in the quarter ended September 30, 2026; total utilisation Rs. 56.59 crore; unutilised amount Rs. 0.00.
Monitoring Agency notes that funds were routed through a monitoring account and then to other bank accounts (overdrafts, EEFC, cash/credit facilities) which caused commingling; management certificates and CA certificates corroborate that utilization aligns with the Offer Document and there is no observed deviation.
Object-wise allocation and progress
Details of objects to be monitored show two main allocations: (i) Setting up a new manufacturing facility – Rs. 47.73 crore; (ii) General corporate purpose – Rs. 8.86 crore; total Rs. 56.59 crore (net proceeds).
Progress by September 30, 2026: Object 1 (Setting up new manufacturing facility) – proposed Rs. 47.73 crore; raised Rs. 47.73 crore; utilised Rs. 47.73 crore; unutilised Rs. 0.00 crore. The quarter recorded Rs. 12.59 crore expenditure during Q2 FY27, contributing to total utilisation of Rs. 47.73 crore by end of quarter.
Notes indicate that expenditure for Q2 FY27 was funded initially from internal funds/overdraft against fixed deposits and later settled from IPO proceeds upon maturity of fixed deposits; overall, the Monitoring Agency assesses that the expenditure is funded from IPO proceeds and no head-by-head deviation is established.
Delay in implementation: Original timeline for completing Set up facility was up to Q4 FY25-26; actual completion noted as Q3 FY2026-27 in accompanying notes; management states the extension is within the extended timeline permitted under the Offer Document. West Bengal regulatory approvals and related delays contributed to the revised schedule.
Notes on object descriptions, verifications and extensions
Object 1 description: Setting up a new manufacturing facility at Mouza-Patinan, etc., with total estimated project cost Rs. 100.22 crore; Rs. 47.73 crore to be utilised from IPO proceeds; remaining Rs. 50 lakh to be funded via borrowings; prior spend of Rs. 2.49 crore up to May 31, 2025.
Object 2 description: General corporate purpose with estimated allocation of Rs. 8.86 crore; eligible uses include investments and ordinary-course corporate needs within SEBI ICDR compliance limits.
Note 1 explains that net IPO proceeds were transferred to a monitoring account and subsequently routed through fixed deposits and overdrafts; accordingly, some commingling occurred, but no deviation from stated objects was observed, with management and CA certificates supporting utilisation.
Note 2 provides that while the RHP indicated commercial production timing, management has noted extension/adjustment to timelines consistent with regulatory and project delays; the monitoring basis depends on management certificates and supporting documents.
Disclaimers, methodology and disclosures
Monitoring Agency's report is based on information provided by the issuer and other reliable sources; it is not an audit and does not constitute an independent verification.
The MA disclaims fiduciary relationships and notes it may have other commercial dealings with the issuer; the report is intended for Indian jurisdiction and not as investment advice.
The report highlights that it should be read in its entirety; selective review may lead to inaccurate assessments, and MA bears no liability for losses arising from the use of the report.