28 Nov 2026 1 filing
Material event and updated timelines
Borana Weaves Limited has been informed by project developer Clean Max Enviro Energy Solutions Limited that the 9.9 MW hybrid power project at Kalikanagar, Gujarat has been delayed.
The first WTG location with a 7.65 MW solar component is now expected to commission before December 31, 2026.
The second WTG location is expected to commission by December 31, 2026, and the third WTG location by March 31, 2027.
The delays are attributed to factors outside the company's control, including the nearby industry hub's inability to secure timely shutdown of the existing 33 kV and 11 kV lines for 33 kV line work, affecting commissioning.
Parties, project and location context
Issuer: Borana Weaves Limited (Scrip Code 544404).
Project developer: Clean Max Enviro Energy Solutions Limited.
Project site: Kalikanagar, Gujarat.
Filing context and date references
This update continues the prior intimation dated November 2, 2026 regarding the delay in commissioning.
Date of the current communication: November 27, 2026 (document date); prior filing date referenced as October 31, 2026.
4 Nov 2026 1 filing
Business Overview
Surat-based integrated textile maker of greige fabrics and PTY, with 4 units.
98% repeat order rate indicates strong customer trust.
Targets 70-80% renewable energy for factory power.
Expansion & Renewables
Unit 4 expansion adds 384 looms; production starts Dec 2026 and Mar 2027.
Funding for expansion through internal accruals and debt.
55 MW rooftop solar is operational; 9.89 MW solar; 19.79 MW hybrid project planned.
Target 70-80% power from renewables.
Financial Performance
Q2 FY27 revenue from operations ₹13,820.13 Lakhs.
Total income ₹13,931.17 Lakhs; QoQ 36.99%.
EBITDA ₹2,537.27 Lakhs; margin 18.36%.
PAT ₹1,615.96 Lakhs; margin 11.69%.
H1 FY27 revenue from operations ₹23,904.03 Lakhs.
H1 EBITDA ₹5,121.51 Lakhs; margin 21.43%.
H1 PAT ₹3,263.95 Lakhs; margin 13.65%.
Cash and cash equivalents ₹-31.3 Lakhs.
Total Assets ₹41,142.65 Lakhs; Total Equity ₹31,413.26 Lakhs.
Borrowings (Non-current) ₹5,555.03 Lakhs; Current ₹2,286.28 Lakhs.
Risks & Cost Dynamics
Margin pressure from POY imports; limited quarterly cost pass-through.
3 Nov 2026 1 filing
No brief for this announcement. Newspaper publications aren’t summarised. View the original using the link below
2 Nov 2026 6 filings
IR appointment
Appointed on 02-11-2026 Finportal Investments Private Limited as IR agency.
Expansion Details
Expansion at Unit 4 to install 384 Water Jet Looms in two phases.
Phase 1: 192 looms by Dec 2026; Phase 2: 192 looms by Mar 2027.
Total installed capacity to 1,596 looms, 459.64 million metres annually.
Current capacity 1,212 looms, 85% utilization.
Investment: Phase 1 Rs. 24.96 crore; Phase 2 Rs. 24.96 crore; total Rs. 49.92 crore.
Financing: internal accruals and debt.
Rationale: broaden product portfolio, attract high-value buyers, improve cost efficiency.
Board approved expansion at meeting held on 02 November 2026.
Change in Registered Office Address
Previous address not disclosed.
New registered office: Plot Nos. B 5/3 to B 5/7/1, Road No. 9, Hojiwala Estate, Sachin, Surat, Gujarat 394230.
Effective date: immediate.
Financial results
Approved the unaudited quarterly and half-year results for the period ended 30 September 2026; Limited Review noted.
Unaudited results cover quarter and six months ended 30 September 2026.
Unit 4 capacity expansion
Approved expansion at Unit 4: install 192 Water Jet Looms; total Unit 4 looms rise to 384.
Funding from internal accruals and debt.
Phase 1 by Dec 2026; Phase 2 by Mar 2027.
Capex per phase Rs 24.96 crore.
Total capex for 384 looms Rs 49.92 crore.
Total installed capacity after expansion: 1,596 looms.
Rationale: broaden product portfolio and attract premium buyers.
Registered office update
Updated registered office address to Hojiwala Industrial Estate, SUSML, Surat.
Investor relations appointment
Appointed Finportal Investments Private Limited as IR agency.
Audit report note
Statutory auditors issued unmodified limited review opinion on interim results.
Key results & governance
Unaudited Q2 and H1 FY27 results ended 30 Sep 2026 approved by Board.
Statutory auditors conducted limited review and issued an unmodified opinion.
Only one reportable segment: Textile.
EPS not annualised for interim periods.
Interim results prepared under Ind AS; figures balancing with June quarter.
Auditor: KSA & Co; Partner Arun Kanodiya.
Delay in project commissioning
Subject: further delay in commissioning of 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat.
First WTG with 7.65 MW solar now to be commissioned before 30 November 2026.
Second WTG to be commissioned by 31 December 2026; third by 31 March 2027.
Delay due to high wind speeds, heavy monsoon, logistics roadwork, and 33/11 kV line shutdown constraints.
Developer: Clean Max Enviro Energy Solutions Limited; latest communication confirms revised schedule.
Follows earlier intimation dated 30 September 2026.
27 Oct 2026 1 filing
Meeting Details
Board meeting scheduled for 02 November 2026 at the Registered Office of Borana Weaves Ltd.
Key Agenda Items
Un-Audited financial results for the quarter and six months ended September 30, 2026 to be considered and approved.
Expansion project at Unit 4: installation of 192 Water Jet looms with production targeted by March 2027.